The Pre-Order Checklist I Run Before Any Commercial Refrigeration Order (After $11,400 in Documented Mistakes)

I have been handling commercial refrigeration service orders for 9 years. In that time I have personally made, and written down, 6 significant mistakes. Total wasted budget: roughly $11,400. Plus two blown deadlines and one customer who came within a phone call of walking away.

Now our team runs this checklist before anyone hits submit on a refrigeration order. It is not theory. Each of the 8 steps below got added because something went wrong first. If you are ordering for a walk-in cooler, a blast chiller, a rack replacement, or a full Bohn system, you can just copy it.

Who this checklist is for

Distributors, mechanical contractors, and facilities people who already sold the job but have not issued the purchase order yet. It covers bohn refrigeration equipment and the adjacent stuff that always gets forgotten: air circulation fans, electrical capacity, and whatever else shares the mech room.

One caveat before you start. This checklist assumes your load calculation is done. If it is not, stop here and go do it. Steps 1 through 8 will not save you from a wrong load.

The 8-step pre-order checklist

Step 1: Recalculate the load. Do not read the old nameplate.

Back in my first year (2017) I did the thing every new guy does. The unit coming out was a 1.5 HP, so I ordered a 1.5 HP. Clean swap, right?

Except the room had been re-insulated two years earlier. The door had moved. Somebody had added six feet of shelving that blocked a coil face. The replacement ran its guts out and never pulled the box down. That one cost $680 in redo and a week of my boss not speaking to me.

The nameplate on the old unit is a clue, not a spec. Run the numbers on the room as it exists today—current wall thickness, product load, door traffic, and the pull-down time the customer actually expects.

Step 2: Match components, not catalog pages

This is where the oversimplification gets people. It is tempting to think that if the nominal tonnage lines up, the pairing works. It does not. The same nominal rating at two different evaporating temperatures produces wildly different duty in the box.

Ask for the actual capacity table that covers your design conditions. Not the marketing page. The table. I pulled the bohn compressor side of a matched set once just to see which evaporator families would actually hold at the design point, and the answer was nothing like what the brochure implied.

The check: evaporator and condensing unit rated together, at your design box temp and your design ambient. On one sheet. Signed off.

Step 3: Lock the refrigerant in writing before you order anything

September 2022. We specified a new unit against one refrigerant and then discovered the existing system, plus the service valves, plus half the piping, were built around a different one. Nobody had written it down. The order sat for 11 days while we argued about who paid for the mismatch.

Put the refrigerant, the metering device type, and the component compatibility statement in the PO. Not in a phone call. Not in a text message the project manager will lose.

Step 4: Get the wiring diagram and the nomenclature sheet on day one

Here is something vendors will not tell you: the model number on the quote and the model number on the equipment you receive can be two different products wearing similar labels. One letter off, and the control box does not match the existing system.

We had that one happen on a 12-piece order. Every single unit arrived with a control configuration that was technically right for the application and completely wrong for the panel it was connecting into. Four extra days of field rewiring.

The check: pull the nomenclature document, decode the model number character by character, and compare it to the wiring diagram in the submittal. If the diagram is not in the submittal packet, that is your first red flag.

Step 5: Measure the service clearance with an actual tape measure

This is the step most people skip, and it is the one that turns a two-hour coil swap into a two-day job.

Will the coil slide out? Will the fan assembly come off? Is there enough room for a tech to get a gauge set on the service ports without lying flat on their back under a leak? Pull the dimensions from the drawing and physically check them against the room. If the room is built, walk it with a tape. Not a photo. Not a guess.

Step 6: Plan air circulation as its own system, not an afterthought

Fans get bought last, installed wherever there is an outlet, and blamed first when the box does not hold temp.

I have watched a Vornado fan get mounted directly in the discharge path of an evaporator because somebody wanted the room to feel less dead. It felt great. It also chopped the coil pattern into a short circuit, and half that cooler never got cold. Same story with a can fan tied into a duct run that dumped air straight back into the return.

The check: sketch the airflow path on the floor plan before you pick a fan. You want movement that sweeps product, not movement that races the evaporator.

Step 7: If a boiler installation shares the mech room, sequence the two trades on paper

First quarter of 2024. Refrigeration contract signed. Boiler installation contract signed separately. Neither document mentioned the other. The boiler crew needed the gas train run along the wall where the condensing unit was going. We moved that unit three times. $2,300 in rework and a three-day slip on a job that should have finished clean.

Do not assume the general contractor is coordinating this. Get a one-page layout showing both scopes, both clearances, and the shared electrical load. Circulate it before either crew shows up.

Step 8: Get lead time, freight terms, and the dock schedule in writing

What most people do not realize is that a quoted standard lead time often folds in buffer the vendor uses to manage their own production queue. It is a planning number, not your ship date.

Confirm four things in the PO acknowledgment:

  • The actual ship date, not the category of lead time
  • Freight terms and who pays for liftgate service
  • Receiving hours at the destination dock
  • Who is responsible for offloading a 900-pound condensing unit

I once approved a delivery to a site that closed at 3:30 in the afternoon. The truck arrived at 4. The unit sat on the street overnight. Nothing was stolen, which was pure luck, but I did spend an hour on the phone explaining it to the customer.

Common mistakes that will bite you later

Treating fit as spec

It fits in the room. It bolts to the pad. That does not mean it was selected correctly for the load. Those are two completely separate questions and nobody in the field will catch the second one for you.

Comparing quotes without comparing configurations

Two numbers on a spreadsheet can look competitive and describe entirely different equipment. Same nominal capacity, different coil face area, different fan motor, different control package. Line-by-line, always.

Forgetting the people downstream

Your installer, your commissioning tech, and the guy who does the warranty call in 18 months are all affected by what you order today. A coil that saves $200 and needs a 90-minute disassembly to service is not a saving. It is a debt.

Why the premium configuration usually wins

To be fair, the budget option is not automatically wrong. Small boxes, seasonal use, tight capital—there are situations where the cheaper pairing is the honest answer.

But on anything a customer walks into, the difference between a properly matched system and a barely adequate one is not measured in invoices. It is measured in whether the product holds temp during a hot Friday rush, and whether the box sounds struggling or just sounds on.

Customers never see the model number. They never see the capacity table or the fan curve. They see one thing: does this room do the job it was supposed to do.

The money you shave off a configuration comes back around as a callback, a complaint, or a relationship that quietly stops generating referrals. The gap between the two options is almost always smaller than the cost of one redo.

Run the list. Write down what you got wrong. That is how the next guy avoids the same eight days of your life.

author-avatar
Gavin Mercer

Gavin Mercer covers plate, shell-and-tube, brazed-plate, and finned heat exchangers together with cooling towers, dry coolers, and evaporative fluid coolers. He applies ASME BPVC Section VIII and PED 2014/68/EU considerations while examining LMTD, overall heat-transfer coefficient, pressure drop, fouling allowance, design pressure, and approach temperature. His work guides thermal engineers and procurement teams through duty verification, material selection, cleanability, water quality, corrosion risk, and total installed cost.